HS2 starts to install new cycle bridge at Offchurch near Leamington - road will be closed for 12-days

HS2 engineers have begun installing a dedicated cycle bridge that will connect the Offchurch Greenway near Leamington to Route 41 of the national cycle network.

The new bridge is part of HS2’s earlier programme of work, completed in October 2025, which included the opening of the nearby Fosse Way bridge and Offchurch Greenway bridge, which carry a road and cycle route across the high-speed railway.

HS2’s construction partner, Balfour Beatty VINCI (BBV), has led the installation of all three bridges which, it says, “together play a vital role in enhancing connectivity for local communities”.

Work on the new cycle bridge started in July 2025.

The new cycle bridge at Offchurch. Credit: HS2placeholder image
The new cycle bridge at Offchurch. Credit: HS2

Over the last eight months, the team has dug out and replaced the old embankment, constructed the supporting abutments and wingwalls, and conducted essential drainage and structural backfill works.

To facilitate the next programme of work, the B4455 Fosse Way, near Offchurch, will be closed until Sunday April 26 to allow the new bridge to be safely lifted and lowered into position, ready to connect to the abutments.

Vicki Lee, HS2 Ltd’s Senior Project Manager said: “All three bridges will play an important role in improving safety and connectivity and I’d like to thank our team of engineers who are working exceptionally hard to deliver this programme of work.

“When the new bridge opens, I’m confident it will be welcomed by cyclists from near and far who visit Warwickshire to enjoy this stunning section of the Route 41 trail.”

The new bridge is forecast to open in September 2026.