The pre-made lift shaft was delivered during the early hours of Wednesday morning (April 23).placeholder image
The pre-made lift shaft was delivered during the early hours of Wednesday morning (April 23).

In Pictures: 450-tonne crane delivered to Warwick railway station to move lift shaft onto the site

A 450-tonne crane was delivered to Warwick railway station yesterday (Tuesday April 22) ahead of moving a new pre-made lift shaft onto the site.

The delivery of the crane and pre-made lift shaft is part of the ongoing accessibility upgrades at the station.

Network Rail engineers have been on-site at Warwick station since spring 2024 to install two new lifts which will help passengers access platforms 1 and 2.

The concrete structure has been made off-site ready to be craned into the correct position at a later stage in the project this summer.

So that the machinery and the new structure could be brought on site, the station car park was shut from 5am on Tuesday (April 22) until 10am today (Wednesday April 23.

These photos were taken by Geoff Ousbey between 10.30pm on Tuesday and 7am Wednesday.

Geoff’s photos shows the large crane and its equipment being delivered and the weights being fitted and levelling up on the crane.

Related topics:
Follow us
© 2026 Iconic Media Group Ltd. All rights reserved.Cookie SettingsTerms and ConditionsPrivacy notice