An ageing bridge over the M42 at Junction 6 which had to be closed to traffic is to be demolished and re-built.
National Highways shut the bridge on the north section of the junction’s roundabout in July because of damage to the concrete and some corrosion of the steel reinforcement of the structure.


Assessments have found that the bridge, which was built 50 years ago, is at risk of further deterioration and strengthening would not provide a long-term solution.
National Highways said it is "aiming to minimise disruption" by demolishing the bridge at the same time as one of the planned closures of the M42 between Junctions 6 and 9 for HS2 works in the coming weeks.


National Highways Head of Network Planning and Development, Ian Doust, said: “Many of the motorways and structures we manage were built over half a century ago and now need renewing or replacing to ensure they remain fit for purpose
“Safety has to be our priority which is why we closed the bridge when we saw such a rapid change in the condition of the structure.
“Investigations showed that the most effective and efficient solution is to demolish the bridge and re-build it to modern standards to keep people and goods moving safely and reliably.”
A 7.5 tonne weight restriction was initially imposed to safeguard the bridge when the structural defect was discovered. But the bridge had to be closed in July after further deterioration was identified.
Plans are now being developed for a temporary bridge to be introduced at the junction until a replacement structure can be installed.
Current diversions around the bridge closure will remain in place until further notice. More information on these can be found online.