Work continues on Northgate junction in Warwick


Phase one, which concentrated around Shire Hall and the Methodist Church saw paving and kerb works on Barrack Street and Northgate Street.
Work is due to be completed on phase two on July 14, which includes taking out the roundabout and removing the Victorian gas lamp which has been sent away for refurbishment.
Advertisement
Hide AdAdvertisement
Hide AdIn order to complete the remainder of the works an extensive traffic and pedestrian management plan has been implemented that turns Saltisford, Northgate and The Butts into a one-way system.


The traffic management layout will stay much the same with the exception that through traffic will be on the lane nearest to Northgate House.
Phase four will also see the installation of a sustainable urban drainage system that has been designed to intercept and manage rain water.
As a result the council’s traffic management company has now been instructed to close Northgate Street access from Northgate and allow
access from Barrack Street only.