Aylesford School in Warwick set to reopen its school buildings after nearly three years following asbestos discovery

Aylesford School in Warwick is set to reopen some of its school buildings after more than two-and-a-half years following the discovery of asbestos on the site.

In September 2023, The Courier and Weekly News published several stories about both Myton and Aylesford Schools in Warwick having to close part of their sites due to concerns over reinforced autoclaved aerated concrete (RAAC).

placeholder image
Read More
'Home of alternative hair and fashion' in Warwick moves to new home

It later turned out that RAAC was not an issue at Aylesford School – but during investigations for potential RAAC, asbestos was then also found in some of the buildings on the school site in Tapping Way.

Aylesford School in Warwick is set to reopen some of its school buildings after more than two and a half years following the discovery of asbestos on the site. Photos by Beth Walsh Photographyplaceholder image
Aylesford School in Warwick is set to reopen some of its school buildings after more than two and a half years following the discovery of asbestos on the site. Photos by Beth Walsh Photography

Since then, Aylesford School has adapted how they have used the site to teach their pupils – including using temporary buildings for classrooms.

The school said contractor Stepnell has been working with them since August 2024 on “reinstating the school buildings following a period of school closure”.

Work has been taking place on the site to remove asbestos and to complete structural repairs.

The school said work has been taking place in phases so that some of the buildings could be reopen while work continues on other parts of the site.

The science labs on the school site will be one of the first areas to reopen. Photo by Beth Walsh Photographyplaceholder image
The science labs on the school site will be one of the first areas to reopen. Photo by Beth Walsh Photography

A spokesperson from Aylesford School said: “The reinstatement project has substantially grown since the contract was signed due to extensive damage caused to the building fabric and services as a result of asbestos removal works.

“Further challenges in the condition of the buildings identified as the programme developed have added further items to the scope of works.

"We have worked closely with the Department for Education to secure additional funding to address the increased scope to allow works to continue and to address critical needs as the reinstatement programme developed.

“The increased scope of works meant that the original completion date of November 2025 was delayed to June 2026.

The science labs on the school site will be one of the first areas to reopen. Photo by Beth Walsh Photographyplaceholder image
The science labs on the school site will be one of the first areas to reopen. Photo by Beth Walsh Photography

“Continuing to operate a live school alongside such an extensive and challenging project has been no mean feat and finally, after over two years of disruption we are reaching a milestone in this project.

“Throughout the programme, Stepnell have recognised the importance of getting our pupils and staff back into these teaching spaces, and they have worked tirelessly to complete parts of their works earlier where possible.

“Over January, the school has worked hard to ensure that all key facilities needed in the reinstated sections of the buildings are safe and working well. This includes furniture, equipment, signage, IT infrastructure, services and other health and safety compliance.”

Reopening areas

Areas of the school are set to reopen this month. Photo by Beth Walsh Photographyplaceholder image
Areas of the school are set to reopen this month. Photo by Beth Walsh Photography

Areas that are set to reopen on the school this month include:

  • 17 classrooms including dedicated SEND spaces
  • Six science laboratories and prep room
  • IT suites and flexible learning areas
  • Reception, student services and welfare facilities

On Wednesday February 4, parents are being invited to take tours around the new facilities.

On Monday February 9, teaching will begin in the science laboratories and after the February half term, all the remaining areas in these areas will be fully reoccupied for teaching.

The final areas of the school are due to be completed and handed back by Stepnell in June 2026.

These areas include:

Areas of the school are set to reopen this month. Photo by Beth Walsh Photographyplaceholder image
Areas of the school are set to reopen this month. Photo by Beth Walsh Photography
  • The assembly hall
  • Office spaces
  • The staffroom
  • Meeting rooms
  • The gym and fitness suite
  • Changing facilities
  • Further student toilets
  • Design and technology and food technology spaces.

Removing temporary classrooms

The temporary classrooms which have been on the site for the past couple of years are also set to be removed.

The spokesperson said: “We have also been working with the Department for Education and Wernick on the removal of the temporary classrooms, which have been in place since December 2023.

“This will be done during the Easter holidays with a period either side for preparation and making good of the surfaces where the units have been in situ.

“We expect there to be minimal impact on the day-to-day running of the school during this process.”

They added: "We recognise the disruption that the essential buildings closure has caused over several years. The resilience and patience of parents, students and staff, in continuing to support the school over this period is greatly appreciated.

"We are all excited to see the new and improved Aylesford School and are looking forward giving students in these fantastic new spaces to learn in.”