End of work on major gateway into Warwick delayed due to 'various challenges'
The end of improvement works to a major gateway into Warwick town centre has been delayed due to ‘various challenges’.
Warwickshire County Council has provided an update on the progress of the works taking place in the St John’s area, which had been due to end this month.
Work started on the project in October, which is part of a wider scheme to improve the traffic management of Warwick town centre.
The aim of the work is to make the area able to cope more with the increased traffic levels between Priory Road and St Nicholas Church Street.


The changes include: one way systems, shared paths for pedestrians and cyclists, upgraded crossings, speed humps and road narrowing, tree removal and planting, as well as parking changes.
Back in December, the council said the project was ‘running well and to schedule’ but now the work looks set to carry on for up to another two months.
This week, Warwickshire County Council said the scheme is ‘progressing well’ but is scheduled for completion in May.
So far work has been completed on upgrading the footway and laying new slabs from The Paddocks along the front of the shops facing the service road, as well as the stretch along Priory Road, which the council said “has been improved to enhance pedestrian and wheeling and cycling access to the town centre”.


Remaining work includes: resurfacing of some of the footways, alterations to the central islands between St Nicholas Church Street and Priory Road, which will include planting and “other public realm improvements”, resurfacing of the St Johns central area, the reconfiguration of parking spaces, upgrades to traffic signals and resurfacing of the vehicle carriageway at all arms of the junction.
The council said there have been “various challenges encountered during the works including the exceptionally high levels of rainfall in January causing problems with the laying and setting of slabs.”
The authority also added that contractors also needed to delay some works activities at various stages to accommodate public and business needs, all of which are important considerations with a scheme such as this.
Cllr Jennifer Warren, Warwickshire County Council’s portfolio holder for transport and planning, said: “The area around St Johns is an important gateway to Warwick and sets the tone for those coming in from Leamington; a town’s appeal is not confined to the town centre but also to the approach.


"On top of that, there is a vibrant community in that area and they deserve good access to shops and to have a choice in how they get to them while the businesses, too, will benefit from the improved access and enhanced look of the area.
“Although the scheme is taking slightly longer than we had initially envisaged, we are still pleased with the schedule.
"There were pauses to the works, in agreement with businesses and local groups to accommodate them.
"That showed a pragmatism and flexibility that was appreciated and a reflection on our commitment to listen and to work towards what suits local stakeholders best.”